Surface Water Treatment Plant

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

About. 

The Surface Water Plant is included in the FY2016 Capital Improvement Program (CIP) and will be a multi-year project, with a duration through 2023. The overall project includes preliminary design, pilot testing, final design, and construction of the first phase (10 MGD) Surface Water Treatment plant and associated water conveyance infrastructure. The Surface Water Plant will treat raw water from the Gulf Coast Water Authority (GCWA) canal and will distribute the water throughout the City via four (4) water transmission lines. This work is estimated to be $145 million in studies, design and construction. In the future, a second 10 MGD expansion is planned.

Scope. Due to the large scope of the project, this project has been divided into three different packages. 

Package 1 consists of a preliminary design effort and Final design services for the Raw Water Intake Pump Station. This will include a var screen device, automated controls and electrical within the pump station and chemical injection as well as advanced water analytical systems. The contract will also include site drainage, outfalls, and detention design per City and Brazoria Drainage District #4 requirements.

Package 2 consists of preliminary design efforts for the major components of the Surface Water Treatment Plant, including: Powder Activated Carbon (PAC) Pre-Treatment, Plate Settlers, Sludge De-Watering, Membranes, Granular Activated Carbon (GAC) post-treatment contactors, Chlorine Facility and Break Tank/ Transfer Pumps and the design, construction and operation of the Pilot Plant.

Package 3 consists of the on-site work for the Ground Storage Tank, the high service pump station/administration building, wastewater forecemain, site security fencing, public and plant entrances/drive and parking, and the off-site components consisting of the transmission pipelines and connections to existing water booster pump stations at FM 521 and Kirby Drive.

Federal Environmental Review Document 

This project will be procured through the Construction Manager at Risk (CMAR) process. 

Schedule Info

   Base Line  Current
 Design Start - Package 1  August 2019  September 2019
 Design Start - Package 2  February 2019  March 2019
 Design Start - Package 3  August 2019  September 2019
 Bid Start  March 2020  January 2019
 Construction Start May 2020   June 2020
 Proposed Construction Completion  December 2022      May 2024

Budget and Funding Info
2024
2023
2022
2021
2020
2019
2018
2017
2016