Mykawa Lift Stations

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

PROJECT OVERVIEW 

About. To accommodate the future widening of Mykawa Road, the relocation of the City's sanitary sewer system became a priority. This project will relocated the Mykawa/Scott Lift Station (LS), abandon the Shank Lift Station, relocate and upgrades the Orange Street Lift Station, and improve and expand the capacity of the collection system within the service area, including the Orange Street gravity line to Hatfield Road. 

Scope. The proposed relocation of the Orange Street LS will expand the capacity of the sanitary sewer service area to accommodate ultimate build-out by increasing the line size of the 2,870 LF of 12-inch gravity sewer main, south of Hickory Slough along Mykawa Road.

The existing Shank Road LS will be decommissioned and replaced with 560 LF of 12-inch gravity sanitary sewer main that will flow towards the new Orange Street lift station. The new lift station will pump through 2,550 LF of proposed 8-inch force main to a new manhole at the intersection of Orange Street and Woody Road. Approximately 2,070 LF of 8-inch sanitary sewer gravity main will be upsized to 12-inch by pipe bursting from the new manhole at the intersection of Orange Street and Woody Road. The upsized 12-inch sewer line will continue along Hatfield Road for approximately 1,200 LF south of Orange Street where it will tie into the top end of the Hatfield trunk sewer line installed in 2015. This reconfiguration removes wastewater flows from the Shank Road area from the Barry Rose Water Reclamation Facility (WRF) service area and sends them to the JHEC WRF service area. The transfer of the wastewater between the two service areas is accounted for in the future expansions of each WRF

The new Mykawa/Scott LS has been designed to collect sanitary sewer flows from the existing service area and some additional flows from the proposed 1,120 LF of 12-inch gravity sanitary sewer north of Hickory Slough and Scott Street increasing the total service area. The proposed lift station will pump through approximately 2,550 LF of new 8-inch force main to a new manhole west of State Highway 35. This lift station discharges into the gravity collection system for the Barry Rose WRF.

Once both lift stations are in service, the existing sanitary sewer system along Mykawa Road will be abandoned. This includes: decommissioning three existing lift stations (Shank Road LS, Mykawa/Scott LS, Orange Street LS) and abandoning in place the existing 10’’ sanitary sewer line along the east side of Mykawa Road making way for the roadway’s expansion.

In summary, the project expands our system while reducing the number of lift stations by one and eliminates the conflicts with the Mykawa Road widening.


Schedule Info

   Base Line  Current
 Design Start   May 2016  May 2016
 Bid Start   August 2017  April 2019
 Construction Start - Package 1    July 2019  August 2019
 Construction Completion - Package 1 February 2020 December 2019
 Construction Start - Package 2 July 2019 September 2019
 Proposed Construction Completion - Package 2 September 2020 December 2020 
 Construction Start - Package 3 July 2019 August 2019
 Construction Completion - Package 3  March 2020 May 2020 