December
Highlights:
The Design contract was awarded to IDS Engineering Group on August 22, 2019. The Construction contract was awarded to Reliance Construction Services (Reliance) in October of 2021. The Notice to Proceed was issued January 31, 2022. The project dealt with increased lead times for waterline fittings due to supply chain issues, that caused the delay in the actual start date to March 21, 2022. On September 19, 2022, the Project Management team met with the residents in a Town Hall type meeting to update the progress of the project and answer questions.
Upcoming Work Items:
- Reliance will continue to install the 48” storm pipe on Mockingbird Lane until they reach Wingtail Way.
- When Reliance reaches Wingtail Way they will move to the east end of Heron Lane, connect to the newly installed BDD4 storm pipe, and begin installation of 48” storm pipe west along Heron Lane.
- The culvert and paving crews will continue to install culverts and driveways between Meadow Lane and Heron Lane.
- Asphalt patches and driveways will be installed as the drainage work is completed on each street.
Read December Memo
July
Highlights:
The Design contract was awarded to IDS Engineering Group on August 22, 2019. The Construction contract was awarded to Reliance Construction Services (Reliance) in October of 2021. The Notice to Proceed was issued January 31, 2022. The contractor had increased lead times for some of the waterline fittings due to supply chain issues, that caused the delay in the actual start date to March 21, 2022.
- The Contractor began installation of the storm pipe in mid May 2022 once the waterline relocation work on Heron Lane was completed and in service.
- Drainage work began at the newly installed BBD4 storm junction box at the east end of Meadow Lane and has proceeded west along Meadow Lane beyond Bluebird Way.
- Reliance presently has 3 crews on site. The pipe crew is currently installing 42” storm pipe on Meadow Lane. The culvert crew is installing the new pipe culverts for the driveways and sidewalks between West Lea Lane and Meadow Lane. And the paving crew is installing the new driveways after the new culverts have been installed. Reliance has been re-grading the ditches as they complete installation of the storm lines and culverts.
- As part of the project BDD4 is expanding the detention basin, installing the pond under drain system and connection to Mary’s Creek. BDD4 has continued to install new 48” drainage pipe and junction boxes along the east edge of the subdivision. They have progressed to the southern edge of the Mockingbird Lane intersection.
Upcoming Work Item:
- Reliance will continue to install the 42” storm pipe on Meadow Lane until they reach Wingtail Way.
- When Reliance reaches Wingtail Way they will move to the east end of West Lea Lane, connect to the newly installed BDD4 storm pipe, and begin installation of 48” storm pipe west along West Lea Way.
- The culvert and paving crews will continue to install culverts and driveways between Meadow Lane and West Lea Lane and Mockingbird Lane.
- Reliance will continue to connect the waterline offsets once they have completed the pressure testing and disinfection process.
Read July Memo
May
Highlights:
- The Design contract was awarded to IDS Engineering Group on August 22, 2019. The Construction contract was awarded to Reliance Construction Services (Reliance) in October of 2021. The Notice to Proceed was issued January 31, 2022. The contractor had a lead time for some of the waterline fittings due to supply chain issues, that caused the delay in the actual start date of March 21, 2022.
- Reliance began construction by installing 12”, 8”, and 6” waterlines along Heron Lane. The waterlines are being relocated because they conflicted with the proposed storm lines.
- Reliance has completed installation of 12” waterline west on Heron Lane from Meadowlark Way to Bluebird Way where it reduced to a 6” line to the end of Heron Lane.
- The Contractor has installed 8” lateral waterlines across Heron Lane on Meadowlark Way and Bluebird Way.
- Residential service connections to the new waterlines along Heron Lane are being installed as the work progresses.
- The Project Team (PM, CM and Engineer) conducted a community outreach meeting in the neighborhood on the evening of May 2nd. The contractor provided a short presentation and the Team answered residents’ questions. The meeting was deemed successful, and no questions remained unanswered by the conclusion of the meeting.
Upcoming Work Items:
- Reliance is currently working to pressure test and sterilize the newly installed waterline offsets so they can be placed into service.
- The Contractor will begin installation of the storm pipe in mid May 2022 once the waterline relocation work is completed and in service.
- Drainage work will start at the newly installed BBD4 storm junction box at the end of Meadow Lane and proceed west along Meadow Lane, turning south on Bluebird Way.
- The contractor intends to have 2 crews, 1 crew on each street and they will re-grade the ditches as they complete installation of the storm lines.
- When the drainage crew installing pipe south along Bluebird Way reaches West Lea Lane they will stop, connect to the BDD4 pipe at West Lea Lane and continue west until they reach the intersection of West Lea Lane and Bluebird Way. At that point they will continue south along Bluebird Way.
Read May Memo