August
Highlights:
- Construction of Ground Storage Tank (GST) has been completed.
- All Welds have been X-Rayed and passed 3rd party inspections.
- The GST has been sandblasted and final paint has been completed.
- All concrete flatwork has been poured and completed throughout site.
- Discharge header has been replaced and new water service has been established to control building.
- All piping has been pressure washed, cleaned and recoated with light blue paint per CH. 290 of TCEQ Regulations.
- GST exterior ladder anti climb cage has been installed.
- Water samples have been taken and passed inspections from Water Production and Plant is in full operation.
- Gas service has been established and generator start up and training has taken place.
- Site grading throughout site has taken place and all exposed soil has been Hydro mulched
- Substantial walk through took place July 28, 2021.
- Punch list items were all small details and have been completed already.
- Balancing Change Order adding $17,525 for additional work pending to close out the project.
Upcoming Work Items:
- Final acceptance is based on acceptance of hydro-mulch sprouting.
- Close out documents will be completed by August 31,2021.
Read August Memo
March
Highlights:
- Contractor continues construction of proposed 400,000-gallon Welded Ground Storage Tank (GST)
- Contractor has completed installation of four (4) duct bank runs connecting the exterior control building with the pre-existing tank and exterior booster pump station.
- Electricity has been reestablished at the facility in preparation in order to test pumps and control building operation.
- Painters arrived onsite March 22, 2021 to begin painting the new Welded Ground Storage Tank.
- The control room is operational, and the existing tank is being brought back on-line in order to resume partial plant operations.
Upcoming Work Items:
- Pipe crew will arrive after completion of painting the GST and complete all connections to pre-existing tank.
- After paint and pipe connection predecessor activities, contractor will begin final site work such as paving and sidewalk installation.
- Water samples will be collected prior to opening the system for operation.
Read March Memo
January
Highlights:
- Existing bolted steel ground storage tank has been removed.
- Two existing hydro-tanks have been removed.
- Gas line underground has been run to generator pad.
- Electrical underground has been run to generator pad.
- Generator pad has been poured and generator has been installed.
- All electrical components in control room have been demoed.
- New electrical systems and control panels have been installed.
- Underground electrical duct banks have been installed and encased in concrete.
Construction activities have uncovered several operational issues affecting plant operations:
- The PLC was not working due to a bad power supply. The project will be replacing the power supply to make the plant operational.
- The tank ring foundation had to be moved to avoid an existing underground gas line which has been determined to be incorrectly located outside of the utility easement. Staff are working with CenterPoint Gas to move their trunk line inside their easement. To keep the project moving forward the project was able to shift the tank over to avoid the gas line and not affect the project.
- One of the 12” water main butterfly valves feeding the plant was non-functioning and must be replaced in order to isolate the plant.
Upcoming Work Items:
- All Electrical conduit and supply conductors will be run into control room.
- The re-located foundation of the ground storage tank will be poured.
- The construction of the ground storage tank will begin.
- The control room will be operational, and the existing tank will be brought back on line in order to resume partial plant operations.
Read January 2021 memo