Bailey Road Expansion

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

From Veterans to Main St (SH 35)

Scope: This project consists of widening the current two-lane roadway to a four-lane lane boulevard section to match the existing roadway cross-section to the east and west. The project will include the addition of a new above grade crossing over the railroad to achieve the desired ultimate width as required in the Thoroughfare Plan. The widening will also include drainage improvements to address the road widening. This project will provide improved vehicular mobility in the east/west corridors by having a four-lane boulevard from HWY 35 to SH 288.

This project is part of the 2019 Bond referendum.

Residents can also register to receive project updates through the City’s e-notification system Everbridge.  Project information is often available through the City’s FaceBook page, Twitter and Instagram accounts as well.  We encourage residents and property owners’ to sign up for the e-alerts and information, please contact Morgan Early, Project Manager, at mearly@pearlandtx.gov.

Schedule Info

Design durations vary per project. Typical Bid schedules run approximately 60 days to advertise, hold pre-bid meeting, respond to any bidder questions and open bids. Under normal circumstances, without irregularities, a bid can be awarded within 30 days of the Bid Date. This could extend another 14 days if there are questions regarding the Bidder’s qualifications. A construction Notice to Proceed (NTP) is generally issued within 10 to 14 days of Award bringing the total process to a little more than 90 days from Advertisement to Notice to Proceed.

Base Line Current
Design Start  August 2019  October 2019
Bid Start  June 2021 February 2023
Construction Start November 2022 November 2023
Construction Completion  November 2024 January 2026
Budget and Funding Info
2024
2023
2022
2021
2020
2019