About. This project consists of the reconstruction of concrete neighborhood streets Orange Circle and Linwood Oaks for 2019. The reconstruction projects are based on priorities derived from the Right-of-Way Assessment and resulting Pavement Condition Index (PCI) and will replace existing concrete pavement with new concrete pavement in the identified neighborhoods. The 2019-20 project includes a Waterline replacement on Orange Circle. 

This project is a part of a larger Street Reconstruction project that also includes Sleepy Hollow subdivision and Sherwood subdivision in the future. 

Scope. The streets within Linwood Oaks subdivision designated for improvement are Briar Circle, Linwood Oaks, and Yupon Circle. This project involves reconstructing these streets with new 6” thick concrete curb & gutter pavement and includes the reconstruction of existing storm sewer inlets at Plum Street. Orange Circle is planned to be reconstructed with new 6” thick concrete curb & gutter pavement and includes the reconstruction of existing storm water inlets on Orange Circle North and Orange Circle South.  This project also includes the replacement of 1000-feet of existing water lines on Orange Circle and approximately 700 feet of water line on Mykawa Road between Orange Street and Orange Circle.

This project is part of the 2019 Bond referendum. 

 

Schedule Info

   Base Line  Current
 Design Start  August 2019  August 2019
 Bid Start  June 2020  July 2020
 Construction Start  October 2020  November 2020
 Proposed Construction Completion May 2021  

Budget and Funding Info
2021
2020
2019