Mary's Creek Lift Station Reconstruction

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

About. This project will replace an aging sanitary sewer lift station that has served the Shadycrest area for 30 plus years. The current facility consists of a dry pit design with pumps and electrical controls located below wet well operational levels resulting in occasional loss of equipment due to wetwell backflows. The new lift station is designed to meet our current standards which will improve reliability by removing the dry pit and moving equipment above ground, improve efficiency with new submersible pumps and reduce maintenance costs.

Scope. The work will consist of the installation of a precast concrete wet well, precast valve box, and installation of City-standard submersible pumps, along with associated piping and electrical and control equipment to completely replace the existing lift station. The scope of work will also include paving repairs, traffic control, and a storm water pollution prevention plan. 

Schedule Info

   Base Line  Current 
  Design Start   July 2018  August 2018 
Bid Start   January 2018  February 2018 
Construction Start   March 2018  August 2019 
Construction Completion  December 2019  March 2020

 

 Base Line  Current 
 Design Start  July 2018  August 2018
 Proposed Bid Start  January 2018  February 2018
 Proposed Construction Start  March 2018  April 2019
 Proposed Construction Completion  April 2019  August 2018

 Base Line  Current 
 Design Start  July 2018  August 2018
 Proposed Bid Start  January 2018  February 2018
 Proposed Construction Start  March 2018  April 2019
 Proposed Construction Completion  April 2019  August 2018

Budget and Funding Info
2020
2019